11-15-2011 10:54 PM - edited 03-07-2019 03:25 AM
Hi
I got this scenario
Server with Two NIC teamed using HP teaming tool. NIC#1 connects to SW1 and NIC#2 connects to SW2
SW1--------------------NIC_1 (SERVER) NIC_2--------------------SW2
Will the config be access-port on Sw1 & Sw2 connecting to Server.
Sw1 & Sw2 are connecting to 3750 as trunk ports
cheers
SAM
11-15-2011 10:59 PM
hi,
Yes, you can configure both the switch ports as a access port and allow the specific VLAN on that.
Thanks
Shashi
11-15-2011 11:09 PM
Hello,
It depends on what mode on nic teaming you are using.
Active/Standby (Nic Teaming)
- You will be fine
Active/Active (Nic Teaming)
- You will get mac flapping for sure.
Solution Connect 2 C3750 switches with the stack cables and then use cross-stack etherchannel features.
HTH,
Toshi
11-15-2011 11:15 PM
Hi Toshi
On Server teaming is active/active; i would like to achieve load-sharing and redundancy. Is teaming on Server similar to link aggregation.
cheers
SAM
11-15-2011 11:23 PM
Hi,
Like I said, you can use LACP protocol on HP but you need to stack C3750 together with the stack cables and then use LACP on it.
HTH,
Toshi
11-15-2011 11:40 PM
Hi Toshi, thanks for replying the post.
There is some confusion. have a look at this
3750--------------Etherchannel--------------------------sw1_3020 < channel-protocol 1 >
3750--------------Etherchannel--------------------------sw2_3020 < channel-protocol 1 >
server_nic1-----------------------sw1_3020
server_nic2-----------------------sw2_3020
Server ( Host_1 ) got Microsoft HyperV running on it and will have 3 Virtual machine running on this Host_1
cheers
SAM
11-15-2011 11:53 PM
Hi Toshi,
attached diagram
11-16-2011 02:38 AM
Sam,
You are going to get a Mac Flapping problem with Active/Active on the server(NIC teaming). Why?
1. Blade Switch is just a switch. Unless you can stack(real) them together to ack as just one switch. It think it doesn't support.
2. You can group uplinks from blade switch to C3750 with LACP features.
3. However, traffic from the server will go through C3750 with 2 paths. This is a problem.
I'd recommend you to use Active/Standby on the Server and do link-state tracking on Blade Switch. In case you lost the uplinks the server should know how to use another one by using this features. It's going to down all downlinks on the server when uplinks were down.
HTH,
Tothi
11-21-2011 11:20 AM
Hi Tothi
How do I configure link-state tracking on blade switch
cheers
SAM
11-21-2011 11:15 PM
Hello,
Check the document. It should have this option.
Toshi