08-26-2021 05:42 AM
Hello Team,
Can I convert production standalone switch to stack switch(2xC9300) by connecting them with stack cables without any downtime for the first active switch? I will change priority on active switch to 15 and then provision the second switch first but would the production switch reload itself once the second switch will be powered on?
08-26-2021 05:47 AM
Yes. This is possible.
08-26-2021 06:03 AM
Is there any other way to have this done without any downtime of production?
Thanks for the reply.
08-26-2021 03:41 PM
@WRB1 wrote:
Is there any other way to have this done without any downtime of production?
Same question. Same answer.
Discover and save your favorite ideas. Come back to expert answers, step-by-step guides, recent topics, and more.