04-04-2019 05:05 PM
Hi guys,
I am planning to create a VDC on Nexus7009 running 7.3.2.D1.3a with N7K-SUP2 / F3 modules.
Just wondering if there is a chance to cause any disruption to the switch operation so that I can determine if this can be done business hours.
The switch currently has single VDC and CPU usage is less than 30%.
Cheers
Solved! Go to Solution.
04-04-2019 08:19 PM
04-04-2019 08:19 PM
04-11-2019 07:07 PM
Hi Francesco,
Thank you for your response.
Creating a VDC didn't cause any issues with the switch operation as you advised.
Cheers
Alex
04-12-2019 09:17 PM