Nexus 5548UP ISSU Question
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
04-15-2013 10:49 AM - edited 03-07-2019 12:49 PM
I have 2 Nexus 5548UP w/ the layer 3 daughter cards on them. As such, ISSU cannot be done, but has anyone had any issues with upgrading the 5k's when they are HA configured with vPCs?
Also, is the install process any different with the layer 3 cards?
Labels:
- Labels:
-
Other Switches
1 Reply 1
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
04-15-2013 02:40 PM
Upgrading 5500 is fairly simple and you need short outage window. Load the OS and the kick start image you want to a flash USB drive. Then copy from USB to internal flash, set your boot variable and reboot. The 5500 boots in less then 5 minutes.
HTH