how to stack 2 switches catalyst 2960 also haw to stack 2 cisco 3750 switches please provide me ?????

1 Accepted Solution

Accepted Solutions

InayathUlla Sharieff
Cisco Employee
Cisco Employee

Hi Mohammed,

Not sure if you have looked at the below links:

Stacking 2960:-

http://www.cisco.com/en/US/prod/collateral/switches/ps5718/ps6406/product_data_sheet0900aecd80322c0c.html

Stacking 3750:

http://www.cisco.com/en/US/partner/products/hw/switches/ps5023/products_configuration_example09186a008078

Easy way:

========

1.  Power up the switch master (ONLY!);

2.   Attach the stacking cable to the rest of the members;

3.  Power up the members ONE-AT-A-TIME and based on the order of your choice.

Example, if switch 2 is the 2nd switch, then power this switch after the master has been powered up and stacking cable has been applied.

Rules-of-the-Thumb:

1.  Ensure all switches are running the same IOS version, same Feature Set (example IP Base);

2.  Once all switches are up, ensure you enable "switch n priority XX";

HTH.

Regards

Inayath

*Plz rate the usefull posts.

View solution in original post

3 Replies 3

InayathUlla Sharieff
Cisco Employee
Cisco Employee

Hi Mohammed,

Not sure if you have looked at the below links:

Stacking 2960:-

http://www.cisco.com/en/US/prod/collateral/switches/ps5718/ps6406/product_data_sheet0900aecd80322c0c.html

Stacking 3750:

http://www.cisco.com/en/US/partner/products/hw/switches/ps5023/products_configuration_example09186a008078

Easy way:

========

1.  Power up the switch master (ONLY!);

2.   Attach the stacking cable to the rest of the members;

3.  Power up the members ONE-AT-A-TIME and based on the order of your choice.

Example, if switch 2 is the 2nd switch, then power this switch after the master has been powered up and stacking cable has been applied.

Rules-of-the-Thumb:

1.  Ensure all switches are running the same IOS version, same Feature Set (example IP Base);

2.  Once all switches are up, ensure you enable "switch n priority XX";

HTH.

Regards

Inayath

*Plz rate the usefull posts.

thank you friend

ASAK Mohamed,

I am glad the information has been helpfull to you.

Could you please mark the query as answered( so that it helps others who has same query.) rather than leaving it as question still  NOt Answered.

Regards

Inayath

*Please rate useful posts and remember to mark any solved questions as answered. Thank you.