We have TMS and TMS Smart Scheduler.  When users schedule meetings in Smart Scheduler for Monday 2/29 they are listed as Tuesday 3/1, I'm assuming due to the Leap year.  However, it shows the correct date when you click on the meeting and within TMS itself.  I've checked to make sure the time-zone settings are correct.  Is this going to problematic on Monday?

2 Accepted Solutions

Accepted Solutions

Patrick Sparkman
VIP Alumni
VIP Alumni

Appears to just be a cosmetic defect with Smart Scheduler, see CSCuy19844.

View solution in original post

Looks like it will sort itself out without issue.  I noticed that today's conferences said they were in progress while appearing as if they were scheduled on March 1st, while all of tomorrow's actual conferences on March 1st are still present under the correct date.

View solution in original post

3 Replies 3

Patrick Sparkman
VIP Alumni
VIP Alumni

Appears to just be a cosmetic defect with Smart Scheduler, see CSCuy19844.

So, I'm curious if it will correct itself after Monday or if each day will be 1 day ahead on the title?

Looks like it will sort itself out without issue.  I noticed that today's conferences said they were in progress while appearing as if they were scheduled on March 1st, while all of tomorrow's actual conferences on March 1st are still present under the correct date.