12-12-2016 06:26 PM - edited 03-19-2019 11:55 AM
Does anyone if there is any issues with enabled in the Scheduled backup for Cisco Unity Connection?
I have a backup scheduled and when I select the enabled schedule, it says 'Enabled successfully' but the status still says "Disabled'. I exit out of this page and go back and it still says 'disabled' so that I am refreshing the page. This happened on the publisher and I managed to make it work by trying the same steps for Unity that no luck on Unity.
Is this a cosmetic bug?
thanks ! - Latenaite
12-12-2016 09:55 PM
Hi Latenaite,
If the backups are actually working as per schedule then this could be cosmetic. You can try a different browser or try restarting the Tomcat service on CUC Publisher.
HTH
Manish
12-14-2016 12:24 PM
Hi Manish,
We will not know until next month when it runs. Note that hte Publisher is fine and it is just on Unity.
I tried IE, Firefox and all seem to be the same. Should I restart the Tomcast service on Unity? Will it impact anything if I restart it during the day?
thanks!
12-14-2016 06:34 PM
Yes, restarting Tomcat on Unity Connection can be tried, it should be okay during normal hours as no critical functions of Unity Connection are associated with it.