cancel
Showing results for 
Search instead for 
Did you mean: 
cancel
1111
Views
0
Helpful
1
Replies

Contact Centre migration

lorenz84gDD
Level 1
Level 1

Hello All,

I'm planning to migrate a contact center based on legacy hardware to a new cisco contact center (uccx).

This CC serves our customers with strict SLAs so I'll have to minimize downtimes.

I'll install a callmanager cluster and migrate phone. I'll have my legacy pbx system connected with a SIP trunk to the new callmanager.

Any ideas on how to proceed with the migration?

Any document for best practices in migrating contact centres?

The biggest requirement is to have all the operators (around 50) migrated to the new CC. So some kind of one shot migration.

thanks all for your help

lorenz

------- have a look to my blog lgrconsulting.com
1 Reply 1

Gergely Szabo
VIP Alumni
VIP Alumni

Hi,

there's no good answer to that.

What I would probably do is to prepare an exact copy of the legacy phone+ACD on the CUCM+UCCX platform, test it extensively, let it run for a while, and when you eliminated all of the problems, switch over.

G.