The existing cluster(s) are configured across 2 DC's. DC 1 is being decommissioned. All the applications instances to move on a new location DC 3.
The versions are NOT going to change nor the setup at DC 2 will be touched. IP addresses will be from different subnet and new HW will be utilized.
Whats the best way to achieve it? I can do PCD for some applications but i am not sure if that can have an impact on DC 2 instances of applications.
Since DC 1 will run parallel till the cutover is planned what should be the best way to achieve pre-cutover tasks.
Applications to be moved are
Thanks
06-12-2018 01:22 PM - edited 06-12-2018 01:22 PM
Hi there
You can actually do this, more a manual method. I still prefer this
For CUCM,
Hope this helps!
Cheers
Rath!
***Please rate helpful posts***
06-21-2018 11:32 AM
06-21-2018 02:29 PM
Hi there
Once you change the PUB to the new ip address you have to change the publisher references in all your secondary nodes. Make sure you run a DRS backup prior to this change, all required changes in DNS and in your network, Schedule an after business hours for this. Post change you have to run thru the post config changes and the followed by a DB replication reset.
Below are the docs for changing the ip address
Hope this helps!
Cheers
Rath!
***Please rate helpful posts***