CUCM Restart Issue After Upgrade

Jason Amick
Level 1
Level 1

We recently did an upgrade from CUCM ver 8.6.2 to 10.5.2.  Everything went smoothly but we did notice after the upgrade that we receive the error message when trying to initiate a reboot/shutdown of our servers via CLI (screenshot attached).  Error states "Restart operation appears to be stuck, Would you like to force restart?".  After that the system restarts/shutdown normally.  I have opened a TAC case and they say that after upgrades this will happen if you do not change the VM specs properly prior to the upgrade which we did.  The only VM spec adjustments needed for us per the upgrade guide was to change the guest OS version to RHELM 6 64-bit and modify the vNIC adapter to VMXNET 3 which we did before initiating the 10.5.2 upgrade.  Seems more cosmetic and does not cause any issues with users but was curious of a root cause/fix. Any ideas? Possible bug? Thanks!!

5 Replies 5

hsood
Cisco Employee
Cisco Employee

Hi Jason,

Can you check if your Vmtools are running fine on that node after the upgrade to 10.5 ?

Regards,

Hitesh

Looks to be fine, i checked as well had our vSphere admin verify.  They are outdated but communicating properly.  Thanks

Jaime Valencia
Cisco Employee
Cisco Employee

Actually, you also had to change the size of the 2nd vDisk to 110 GB

Step 2   (Optional)For an upgrade from 9.x or earlier, if you need to increase the vDisk space to meet the space requirements of a refresh upgrade, install the following COP file:

ciscocm.vmware-disk-size-reallocation-<latest_version>.cop.sgn

http://www.cisco.com/c/en/us/td/docs/voice_ip_comm/cucm/upgrade/10_0_1/CUCM_BK_U4214F9D_00_upgrade-guide-cucm-100/CUCM_BK_U4214F9D_00_upgrade-guide-cucm-100_chapter_011.html

http://www.cisco.com/c/dam/en/us/td/docs/voice_ip_comm/uc_system/virtualization/virtualization-cisco-unified-communications-manager.html#v10

I see that every once in a while even in my lab, where most servers where installed on the major base version, and I just update them with SU's. I also see that when I try to shutdown the server, it seems like something times out and then it's forced to complete when you tell it to force the shutdown/restart, but I've never seen any issues in the machines, and it doesn't happen all the time, at least for me.

HTH

java

if this helps, please rate

I read that as well in the upgrade guide but it was optional and we had enough space in the common partition to perform the upgrade so we chose not to adjust the vdisk space. Per the notes for a 10.x deployment a vDisk 2 x 80 is a valid config. Thanks!!

http://www.cisco.com/c/dam/en/us/td/docs/voice_ip_comm/uc_system/virtualization/virtualization-cisco-unified-communications-manager.html#10000userVM

Upgrades from 8.x VMs with 2x80GB vdisks to 9.1 or higher are not required to change the vdisk. 9.1 and higher will support these two-vdisk options: 2x80GB and 1x80GB+1x110GB (where auto-grow COP was used on second vdisk).

Rob Huffman
Hall of Fame
Hall of Fame

Hi Jason,

Maybe it's related to this "Open" (Sev.-4) bug;

IM & P system restart operation getting stuck
CSCur89511
Symptom:
CUCM IM&P "utils system restart" CLI command reports "Please Wait Restart operation appears to be stuck"

Conditions:
Using the "utils system restart" CLI command.

Workaround:
Use the force restart option.