12-23-2024 03:28 AM
Hi everyone,
I have a C1000-8FP-2G-L where almost once a week the sys led starts showing red led.
While reading the data sheet i found that red sys led means this "The switch failed ACT 2 verification. The configuration running on the switch is not compatible with the running software. Switch is not functioning properly. "
I cannot understand why it is happening, switch version is 15.2(7)E4. Reloading the switch helps for some days/weeks, but after some time the situation ends up being the same.
Can anyone helps?
Thanks, Noemi
Solved! Go to Solution.
12-23-2024 04:16 AM
Contact Cisco TAC and organize for an RMA.
The ACT2/I2C chip has failed. This is a known issue.
12-23-2024 04:16 AM
Contact Cisco TAC and organize for an RMA.
The ACT2/I2C chip has failed. This is a known issue.
12-23-2024 05:29 AM
Hi Leo, thanks a lot for your answer.
Noemi