Hi all,
i need to put again in production 4x 2960 swithes,which were disconnected by error.
The switches were stacked in 2x 2960 stack.The problem is that now i have only 1 switch available per stack,because the two slaves were sent to another company branch.
My question is,if i stack two different switches to the two different stack,do i need to do something on new switches configuration?Do i need to restore factory default on both or when i connect to stack,switch automatically take the master configuration?
Thanks for your help!
Regards,
M.
Solved! Go to Solution.
04-22-2022 06:12 AM
04-22-2022 07:45 AM - edited 04-22-2022 07:46 AM
Hello
1) power up both switch's separately ( not connected) and delete the following.
delete flash:vlan.dat
delete flash:config.txt
reload
2) Power up first switch
conf t
switch 1 priority 15
end
wr mem
reload
3) Once first switch has reloaded attach second switch via the stacking cables and power up that up also
You should now have a stack of two switches.
04-22-2022 04:08 AM
It is a good idea to factory reset them. Also, make sure all of them are in the exactly same software version and make sure those new switches has not higher priority so that then can become the master of the stack.
switch stack-member-number priority "new-priority-value"
Make sure the sequency is OK so that your inteface slot will be right.
04-22-2022 04:34 AM
HI Flavio,
thanks for your reply.
So,if i understood correctly the flow,first of all factory reset new switches,then stack them with the masters and at the end of this process,put 2x2 cisco 2960 stack in production?
Thanks in advance!
04-22-2022 05:08 AM
Factory reset them. Before connect them to the stack, check the priority value. Connect them in the power, use a console cable and them check the priority. Of couse, you need to know which priority the master is using so that you can ajust the slave.
After that, check the version. Put them on the same version, exactly.
Then, join them to the stack.
04-22-2022 05:32 AM
Hi,
thanks for reply.
But is it possible to modify the priority before joining the stack?
Because i'm trying to perform #show switch on a single switch and no output.
Thanks in advance!
04-22-2022 06:12 AM
It can be the version.
I am reffering to this doc:
04-22-2022 07:45 AM - edited 04-22-2022 07:46 AM
Hello
1) power up both switch's separately ( not connected) and delete the following.
delete flash:vlan.dat
delete flash:config.txt
reload
2) Power up first switch
conf t
switch 1 priority 15
end
wr mem
reload
3) Once first switch has reloaded attach second switch via the stacking cables and power up that up also
You should now have a stack of two switches.
Discover and save your favorite ideas. Come back to expert answers, step-by-step guides, recent topics, and more.
New here? Get started with these tips. How to use Community New member guide