08-05-2024 07:38 AM
Hello,
I have two cisco switch C9300-48UXM version image 17.06.04 mode install and the same license
I connected two stack cables (Data) and I chose a switch with the higher priority I put it 15
afterwards I restarted the two switchs
unfortunately they are not stacked Despite the two switches and the stack cables are new, i used other stack cable but the same issue someone have idea
Error message:
*Aug 5 13:13:30.094: %STACKMGR-6-STACK_LINK_CHANGE: Switch 1 R0/0: stack_mgr: Stack port 1 on Switch 1 is cable-not-connected
*Aug 5 13:13:30.094: %STACKMGR-6-STACK_LINK_CHANGE: Switch 1 R0/0: stack_mgr: Stack port 2 on Switch 1 is down
*Aug 5 13:13:30.094: %STACKMGR-6-STACK_LINK_CHANGE: Switch 1 R0/0: stack_mgr: Stack port 2 on Switch 1 is cable-not-connected
*Aug 5 13:13:30.626: %STACKMGR-4-SWITCH_ADDED: Switch 1 R0/0: stack_mgr: Switch 1 has been added to the stack.
*Aug 5 13:13:32.823: %STACKMGR-4-SWITCH_ADDED: Switch 1 R0/0: stack_mgr: Switch 1 has been added to the stack.
*Aug 5 13:13:34.907: %STACKMGR-4-SWITCH_ADDED: Switch 1 R0/0: stack_mgr: Switch 1 has been added to the stack.
*Aug 5 13:13:34.908: %STACKMGR-6-ACTIVE_ELECTED: Switch 1 R0/0: stack_mgr: Switch 1 has been elected ACTIVE.
Switch#show switch neighbors
Switch # Port 1 Port 2
-------- ------ ------
1 None NoneSwitch#show switch stack-ports
Switch# Port1 Port2
----------------------------
1 DOWN DOWN
08-05-2024 07:57 AM
Hi,
Try following the configuration guide below:
HTH
08-05-2024 08:36 AM
Thank you for your responsiveness, I followed this document
this is the first time I encountered an error message like this
08-05-2024 08:53 AM - edited 08-05-2024 09:02 AM
Make sure to connect the switches using 2 stacking cables. This way, if one is bad, the other one can function.
Also, make sure the cable is inserted all the way into the slot.
HTH