09-23-2013 07:51 AM - edited 03-07-2019 03:37 PM
Here is my dilemma. I have a 6500 VSS pair and have been told I cannot perform an eFSU upgrade from SXI4a to SXJ4 something about too big of a jump in IOS trains. I had a test VSS pair (that unfortunately is no longer test pair and in production, or I'de be testing my eventual question) and was able to verify that in fact I cannot go from SXI4a to SXJ4 directly without incurring an 8 minute loss of connectivity while one sup reloads even with dual-homed devices since I am unable to perform an eFSU and had to test an FSU upgrade. So I was wondering if any of you out there would know if it's possible to perform an eFSU from SXI4a to SXI8a then to SXJ4 to not have any downtime
Thanks in advance
Matt
09-23-2013 08:42 AM
Hi,
In principle, there is a document so-called EFSU Compatibility Matrix...
You can find it under the "Cisco Catalyst 6500 Series Switches Release Notes" section:
http://www.cisco.com/en/US/products/hw/switches/ps708/prod_release_notes_list.html
SX SY EFSU Compatibility Matrix
So, according this document the:
But, this is just a document (and quite useful), so...
09-23-2013 09:44 AM
Thanks!
05-01-2014 12:42 AM
Dear Matt
R u able to performed the upgrade on your VSS pair using EFSU
What modules you are using in the chassis ?
Did u notice any modules reset/reload during switchover in ISSU run version step.
Please share the experience.
I also need to upgrade the VSS with 6513/VS720-10G.
05-03-2014 05:50 AM
Dear Matt
R u able to performed the upgrade on your VSS pair using EFSU
What modules you are using in the chassis ?
Did u notice any modules reset/reload during switchover in ISSU run version step.
Please share the experience.
I also need to upgrade the VSS with 6513/VS720-10G.
05-03-2014 05:57 AM
Dear Matt
R u able to performed the upgrade on your VSS pair using EFSU
What modules you are using in the chassis ?
Did u notice any modules reset/reload during switchover in ISSU run version step.
Please share the experience.
I also need to upgrade the VSS with 6513/VS720-10G.
05-03-2014 05:59 AM
Dear Matt
R u able to performed the upgrade on your VSS pair using EFSU
What modules you are using in the chassis ?
Did u notice any modules reset/reload during switchover in ISSU run version step.
Please share the experience.
I also need to upgrade the VSS with 6513/VS720-10G.
Discover and save your favorite ideas. Come back to expert answers, step-by-step guides, recent topics, and more.
New here? Get started with these tips. How to use Community New member guide