08-05-2017 05:45 PM - edited 03-08-2019 11:37 AM
I have 2x3850 switch in stack. One of the switch got removed from stack.
Current state of that switch is Removed.
Its running 03.06.06E.
I removed all the stack cables and reloaded ,shut down and connected stack cables again.But when it tries to syn same issues.
I see below in the logs.
%PLATFORM_HA-4-RELOAD_PEER: Reloading the Standby, due to ConfigSync (Bulk Sync Failure)
%STACKMGR-1-RELOAD_REQUEST: 2 stack-mgr: Received reload request for switch 1, reason Bulk Sync Failure
08-05-2017 06:03 PM
There is a line of configuration that goes like "switch 2 provision <SWITCH model>" remove this and save the config.
08-05-2017 06:10 PM
There are 2 lines,issue is with sw1 so which one should i remove? What does removing this line do?
switch 1 provision ws-c3850-48t
switch 2 provision ws-c3850-48t
08-05-2017 07:36 PM
There are 2 lines,issue is with sw1 so which one should i remove?
Post the complete output to the command "sh switch detail".