02-20-2017 12:24 PM - edited 03-08-2019 09:25 AM
Hi all,
Okay so I have the following problem. I have a stack. Member 1 - 2960-S and member 2 is a 2960-X. Originally I had all ethernet cables plugged into member 1. This evening member 1 failed so I removed all the ethernet cables and plugged them into member 2 (including port channel to the core). So connectivity is restored now.
I want to remove member 1 now and replace it with a 2960-X that I am busy prepping as we speak. What is the best way to do this and would I loose connectivity? I am concerned about down time.
Thanks in advance.
Solved! Go to Solution.
02-20-2017 12:48 PM
Hi,
Follow this link to add the new switch to the stack
Before connecting the new switch to the stack, make sure it is turned off.
http://www.cisco.com/c/en/us/td/docs/switches/lan/catalyst2960x/software/15-0_2_EX/stack_manager/configuration_guide/b_stck_152ex_2960-x_cg/b_stck_152ex_2960-x_cg_chapter_010.html#task_1177470
HTH
02-20-2017 12:48 PM
Hi,
Follow this link to add the new switch to the stack
Before connecting the new switch to the stack, make sure it is turned off.
http://www.cisco.com/c/en/us/td/docs/switches/lan/catalyst2960x/software/15-0_2_EX/stack_manager/configuration_guide/b_stck_152ex_2960-x_cg/b_stck_152ex_2960-x_cg_chapter_010.html#task_1177470