10-15-2020 01:30 PM
Hello, we have a UCS 5108 chassis with 4 power supplies installed and properly connected to the electrical source as follows:
Power Supply 1 and Power Supply 2 connected to circuit A
Power Supply 3 and Power Supply 4 connected to circuit B
Due to an error, the power policy was set to N + 1 and the chassis was released in production.
Now we want to change that setting to set it to GRID mode.
Is that change in configuration from N + 1 to Grid disruptive?
Thanks for the help you can give me on the subject.
Solved! Go to Solution.
10-15-2020 01:35 PM
This change should not be disruptive, however, we always recommend changes during scheduled maintenance windows as a best practice.
10-15-2020 01:35 PM
This change should not be disruptive, however, we always recommend changes during scheduled maintenance windows as a best practice.
10-15-2020 01:44 PM
Thanks for your help and for your advice.