05-30-2007 05:45 PM - edited 07-03-2021 02:08 PM
We have WCS Base + Location and are setting up our heat maps. We have a mostly re-enforce concrete wall facility. If we add the thick walls to areas that has walls the heat maps report coverage holes. The traps are not reporting holes. and preliminary surveys do not show holes. Question, are the Map tools just for prediction or should we using different walls?
05-31-2007 05:27 AM
Hi Michael,
I would stick with the walls the way they are. As you have correctly noted the Heat Maps are just a tool to be used in conjunction with other available tools. The more important one being the "site survey".
Just my two cents :)
Rob
06-07-2007 08:49 AM
Also, I believe that the WCS planning tool uses the worst case scenario setup for your access points. Granted, you are not in the planning mode, but the policies still apply.
Discover and save your favorite ideas. Come back to expert answers, step-by-step guides, recent topics, and more.
New here? Get started with these tips. How to use Community New member guide