Hello  Everyone,

I have below two CUCM, one used for Primary and both er for redundancy,

My question  do we need VMWAR Software for Two Server or one Software  that's enough :

 

1 Server Call manager       
1.1 BE6K-M6-K9 Cisco Business Edition 6000 (M6) Appliance, Export Restr SW   2
1.2 CON-SNT-BE6K6KHW SNTC-8X5XNBD Cisco Business Edition 6000 (M6) Applian   2
1.3 CAB-9K10A-UK Power Cord, 250VAC 10A BS1363 Plug (13 A fuse), UK   4
1.4 VIRT-LIC-NONE Do not factory-load a virtualization software license   2
1.5 BE6K-CPU-M6 Intel 4310T 2.3GHz/105W 10C/15MB DDR4 2667MHz   2
1.6 BE6K-RAM-M6-M5 16GB RDIMM SRx4 3200 (8Gb)   8
1.7 BE6K-RAIDCTRLR-M6 Cisco 12G SAS RAID Controller w/4GB FBWC (16 Drv) w/1U Brkt   2
1.8 BE6K-DISK-M6 600GB 12G SAS 10K RPM SFF HDD   12
1.9 BE6K-PSU-M6 Cisco UCS 1050W AC Power Supply for Rack Server   4
1.10 BE6K-TPM-M6 TPM 2.0, TCG, FIPS140-2, CC EAL4+ Certified, for M6 servers   2

For the below software I will order two servers,  is the software enough for two CUCM??

 

1.1 VMW-VSP-STD-1A= VMware vSphere 8 Std (1 CPU, 32 Core) 1-yr, Support Required   1
1.2 CON-ISV1-VSXSTD1A VSphere Standard for 1 CPU; ANNUAL List 1-YR Reqd   1
1.3 UCS-VMW-TERMS Acceptance of Terms, Standalone VMW License for UCS Servers   1

thank you

2 Accepted Solutions

Accepted Solutions

Assuming that you mean VMware? If so you should have a license per server. I’m not an expert on the BE bundle, but from what I understand it should come with all the licensing that you need, including virtualisation.



Response Signature


View solution in original post

Virtualization is no more bundled with BE and it must be ordered separately.



Response Signature


View solution in original post

3 Replies 3

Assuming that you mean VMware? If so you should have a license per server. I’m not an expert on the BE bundle, but from what I understand it should come with all the licensing that you need, including virtualisation.



Response Signature


Thank Roger,

yes you alright, I need VMW-VSP-STD-1A  for Each CPU , each server should have separate Software.

 

thank you again   

Virtualization is no more bundled with BE and it must be ordered separately.