07-01-2004 08:02 AM - edited 03-13-2019 05:29 AM
My company is thinking about installing 4 Call Managers in one cluster, two CCMs on the U.S. East Coast, two CCms on the West Coast. I am aware of the 40 ms max RTT time requirement. How much BW do I need for a company of approximately 3000 users, split between coasts. We were thinking about separate clusters, but having one gives us a common directory without having to us AD and provides more redundancy between coasts. Does anyone have any real-life implementation experience with this, or a good estimate? Thanks!
07-01-2004 08:11 AM
Hello,
If you look at the design guide it will give you a good idea .
Below is the link.
cisco.com/go/srnd and look for the design guide.
Thanks,
Radhika
07-01-2004 09:40 AM
I see what you mean. The theoretical maximum is 1860 miles. The distance between my locations is more than that.. Mapquest says 2900 miles.
Thanks!
George
07-01-2004 10:37 AM
It's not about distance, its about round trips. If you can ping from one to another locations, less than 150ms (guessing, I forgot exact time), it will be fine.
07-05-2004 08:06 PM
under 100ms delay 1 way good 200ms dont go higher.
07-06-2004 05:09 AM
A call with Cisco engineers since posting my original message says prety much the same thing. Right now we are looking at a rtt of 96 ms, so I think we are going to give it a try. Thanks for the reponses!