08-26-2020 04:46 AM
We are about swap out just the chassis (not changing modules) on a 6509-v-e switch. This device sits in a VSS pair. I don't see any specific caveats in doing this in the documentation but is there anything to watch for, verify if we are just doing a straight replacement of the chassis only? The existing sups and line cards from the current device will be going back in.
Power down, put in new chassis, replace cards and sups and power up is the plan.
Thanks for any info.
Solved! Go to Solution.
08-26-2020 05:08 AM
changing the chasis with same specification of Power, i do not see any issue, make sure you change the chasis, and and test all the moduies booted correctly, before joining to VSS domain again.
08-26-2020 05:08 AM
changing the chasis with same specification of Power, i do not see any issue, make sure you change the chasis, and and test all the moduies booted correctly, before joining to VSS domain again.
08-27-2020 03:07 AM
Thank you. Turns out, this is not a VSS configuration, so makes life a little easier. Thanks for your response.
Robert
08-28-2020 12:49 AM
Everything went well with no issues. Except the weight of box
Thanks again.
Robert
08-28-2020 01:03 AM
Agreed - changed myself once-- with rollers - Lucky it was bottom of the rack.
08-27-2020 03:25 AM
You are lucky if not VSS - easy win then for you.